Ravensdown Dosing System and Tank Replacement

Ravensdown

Dosing System and Tank Replacement

6 pH Maintained At All Times

Problem

The Ravensdown Dunedin plant would have periods of time where they would have to report low pH of their discharged stormwater. These low spikes were due to acid spills or run off being rinsed off by rain water into the storm water system. Ravensdown were not required by consent to pH correct this stormwater but felt it was part of their licence to operate and therefore responsibility to ensure only neutralised water was exiting the plant.

Solution

Initially, DETA developed the dosing design and then business case with local contractors. DETA worked to design the simplest possible solution that would achieve the brief of only pH neutral water exiting the site. DETA engaged with site staff from management to operations to ensure that all points of view were considered. The business case was submitted by Ravensdown and approved late in 2017. Upon approval of the business case DETA offered to complete the project as a turn key solution. This was beneficial to Ravensdown as it removed extra administration work required to track the project and send PO’s to contractors. DETA took full responsibility in procuring the required equipment and scheduling the contractor work. DETA worked with Ravensdown employees to oversee the commissioning and first week’s operation of the system to ensure the pH correction was working as required.

Outcome

The project was delivered on budget and had a smooth installation due to regular contractor communication. With a strong involvement from Ravensdown’s process engineers and buy in from contractors the sites stormwater has not dropped below a pH of 6 since the commissioning of the project. With continued results Ravensdown will be able to report positive water quality for the foreseeable future. As part of the project DETA also replaced the caustic tank with a HSNO certified one to meet ongoing HSE and compliance requirements.

 

Industrial plant at dusk with glowing smokestacks, steel structures, and city lights under a cloudy sky
by Jeff Smit 9 June 2026
Move beyond grid constraints. Discover three asset-backed engineering paths to operationalise demand-side flexibility and protect your production uptime.
Industrial refinery at dusk with glowing orange sky and sprawling metal pipes
by Jeff Smit 4 June 2026
Does the government's gas loan scheme actually add up? Jeff Smit breaks down the NZ energy crisis and the real infrastructure barriers stalling industrial transition.
Industrial facility with large metal tanks, rooftop equipment, and a parked truck on a wet lot.
17 May 2026
Volatile diesel prices and declining gas fields are changing the game. Learn why Australasian industry must act now to de-risk CapEx and electrify.
Show More